UK nuclear engineering advances: Sizewell C and the first Rolls-Royce SMRs

Sizewell C reached its final investment decision in July 2025, and Rolls-Royce SMR signed a contract in April 2026 to deliver three small modular reactors at Wylfa. Here is where the UK's nuclear programme stands.

SMR Presentation Template

Key points

• UK government commits £16.7bn to nuclear engineering projects, including Sizewell C (£14.2bn) and SMR development (£2.5bn) • Rolls-Royce SMR selected as the preferred technology provider for three 470MW modular reactors targeting mid-2030s deployment • Sizewell C will deliver 3.2GW capacity using proven EPR technology, supporting 70,000 construction jobs • SMR program represents the first major European deployment of factory-built nuclear modules with 60+ year operational life • Combined projects could position the UK as a leader in next-generation nuclear engineering if technical and schedule targets are achieved • International SMR market projected to reach £500bn by 2050, offering export opportunities for British nuclear engineering firms

Update: this story was first published in June 2025, when the government set out its spending plans. Since then Sizewell C has reached its final investment decision, and Rolls-Royce SMR has signed a contract to deliver the UK’s first small modular reactors (SMRs).

Sizewell C

In July 2025 Energy Secretary Ed Miliband signed the final investment decision for the Sizewell C nuclear power plant. The plan is for Sizewell C to feature two EPR reactors producing 3.2 GW of electricity, at a capital cost of around £38 billion in 2024 prices. That is enough to power the equivalent of around six million homes for at least 60 years.

The government is taking an initial 44.9% stake, making it the single biggest equity shareholder.

The first small modular reactors

In April 2026 Rolls-Royce SMR and Great British Energy – Nuclear signed a contract that enables work to start immediately on the UK’s first SMRs. Three Rolls-Royce SMRs are being delivered at Wylfa, on the island of Anglesey in North Wales, where a Magnox plant is being decommissioned. The site could potentially host up to eight SMRs.

The design is a 470 MWe design, built around the idea of making reactor parts in a factory and assembling them on site. The National Wealth Fund is committing up to £599 million to Rolls-Royce SMR, and £2.6 billion was allocated in the 2025 Spending Review to enable the contract and wider programme delivery. A final investment decision is expected to be taken in 2029.

SMR facts

  • Unit capacity: 470 MWe per reactor
  • Units being delivered at Wylfa: three
  • Wylfa site potential: up to eight SMRs
Diagram of a small modular reactor power plant

The Born to Engineer team

Credit via gov.uk

Tagged