
Construction & Infrastructure
HS2 has lifted the front section of tunnel boring machine Sushila out of the Green Park Way shaft in Greenford, ending a five-mile drive for the Northolt Tunnel.
HS2 has successfully completed the complex Tunnel Boring Machine (TBM) ‘Sushila’ extraction at the Green Park Way site in Greenford, West London. The massive machine was lifted from the ground on Saturday, March 15,[1] following its completed tunnelling mission beneath the capital.
The engineering operation involved removing the TBM’s cutter head, front shield, and middle shield-weighing a combined 850 tonnes-in a single lift operation.[2][3] Engineers employed a specialized 750-tonne gantry crane to extract the machine components from the ventilation shaft where the TBM had completed its journey.[4]
The extraction marks the final phase of Sushila’s operational life on the Northolt Tunnel project, concluding its underground journey in December 2024.[5] The TBM’s removal required precise planning and coordination to bring the massive components to the surface safely.
“Extracting a machine of this size presents significant engineering challenges,” explained Malcolm Codling, HS2’s Client Director for London Tunnels. “The teams had to carefully plan each aspect of the lift to ensure the structural integrity of both the machine and the shaft during the extraction process.”
Tunnel boring machines like Sushila function as complete underground factories, combining multiple engineering systems in one massive apparatus:
The extracted components represent only part of the entire TBM assembly, which has impressive specifications:
The extraction process required several preparatory steps:
James Richardson, Managing Director of SCS JV (the joint venture of Skanska, Costain, and STRABAG), noted: “The extraction of TBM Sushila demonstrates the technical expertise of our engineering teams. Lifting components of this size from an underground position requires exceptional planning and execution.”
The extraction follows the successful completion of Sushila’s tunnelling mission. Launched from West Ruislip in October 2022,[10] the TBM completed its 5-mile journey in December 2024,[11] breaking through at the Green Park Way ventilation shaft.
During its underground operation, Sushila:
The TBM was the first of four machines to complete its section of the 8.4-mile Northolt Tunnel,[14][15] which will eventually carry high-speed trains between HS2’s Old Oak Common station and West Ruislip.
The TBM extraction was planned to minimize community disruption, with operations coordinated to reduce noise and traffic impacts in the surrounding Greenford area. Throughout its tunnelling journey, excavated material was transported to designated areas west of the tunnel, eliminating the need for removal by road transport.[16]
These disposal areas will be repurposed as wildlife meadows and wooded areas, forming part of HS2’s Green Corridor initiative, creating ecological benefits along the railway route.[17]
The machine holds local significance and is named after Sushila Hirani, a local school teacher selected by a community school to receive this honour.[18] After extraction, specific components may be refurbished for future tunnelling projects, while others will be recycled, aligning with HS2’s sustainability commitments.
This extraction marks an essential milestone in the Northolt Tunnel project. Three additional TBMs-Caroline, Emily, and Anne-are currently operating in the tunnel and will complete their journeys at Green Park Way in the coming months.[19]
With the UK Chancellor confirming in October 2024 that construction of HS2’s Euston Tunnel would proceed,[20] two additional TBMs, Karen and Madeline, are being assembled in the underground box at the Old Oak Common station site to continue tunneling eastward.[21]
The completion of the Northolt Tunnel will connect with the tunnel section from Old Oak Common to Euston, completing the London portion of the high-speed rail network.
“The successful extraction of Sushila brings us one step closer to delivering this transformative infrastructure project,” said Codling. “Each milestone demonstrates our commitment to building a transportation network that will serve generations to come.”
Credit via hs2.org.uk
HS2 tunnelling machine lifted from ground after drive under capital
crane-lifted from the vent shaft in one piece
Checked 22 October 2026
HS2 tunnelling machine lifted from ground after drive under capital
weigh 850 tonnes
Checked 22 October 2026
HS2 TBM Sushila removed following Northolt tunnel excavation
850 t
Checked 22 October 2026
HS2 TBM Sushila removed following Northolt tunnel excavation
750 t gantry crane
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
reached the Green Park Way vent shaft in Ealing yesterday [19th December 2024]
Checked 22 October 2026
HS2 Marks Completion of 5-mile Drive on Northolt Tunnel
with a 9.84-m diameter cutterhead
Checked 22 October 2026
HS2 Marks Completion of 5-mile Drive on Northolt Tunnel
The TBM used for the excavation is 160 meters in length
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
a cutterhead 9.84metres in diameters
Checked 22 October 2026
HS2 Marks Completion of 5-mile Drive on Northolt Tunnel
It weighs approximately 2,050 tonnes
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
Launched in October 2022 from West Ruislip, TBM Sushila has excavated over 1.2 million tonnes of earth
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
HS2 engineers are celebrating completing a successful 5-mile tunnelling drive under the capital.
Checked 22 October 2026
HS2 Marks Completion of 5-mile Drive on Northolt Tunnel
excavated over 1.2 million tonnes of earth
Checked 22 October 2026
HS2 Marks Completion of 5-mile Drive on Northolt Tunnel
installed 4,217 tunnel rings
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
was the first to start and is the first to complete the journey
Checked 22 October 2026
HS2 tunnelling machine lifted from ground after drive under capital
an 8.4-mile tunnel being built by four TBMs
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
All the earth excavated by the machine has been placed in two areas west of the tunnel
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
These areas will be turned into wildlife meadows and wooded areas as part of HS2’s Green Corridor.
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
Sushila, named after a local school teacher,
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
with three further TBMs in operation on the Northolt Tunnel
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
At the budget in October, the Chancellor announced that the construction of HS2’s Euston Tunnel would go ahead.
Checked 22 October 2026
It’s in the can: HS2 tunnelling machine finishes its 5-mile journey
the two machines which are being assembled in the giant underground box at Old Oak Common station site
Checked 22 October 2026