HS2's Second Giant Tunnel Boring Machine Assembled and Set to Start Digging Into Birmingham
HS2 has finished assembling its second 1,600-tonne tunnel boring machine, which will start digging the second bore of the Bromford Tunnel into Birmingham next spring.
Key points
- Specialists complete the assembly of HS2's second 1,600-tonne tunnel boring machine (TBM)
- The machine will start digging the second bore of the 3.5-mile Bromford Tunnel into Birmingham next spring
- Joins existing TBM "Mary Ann" already 500m deep into first bore excavation
- The majority of new TBM was reused from "Dorothy" after completing the previous HS2 tunnel
- The 90-person crew will operate TBM boring 24/7 to hit 16 monthly timelines per bore
- 41k concrete segments to line the completed tunnel, precision fabrication for safety
- HS2 at peak construction with nearly 10k workers rapidly advancing infrastructure
The UK’s High Speed 2 (HS2) rail network took a significant step forward this week as specialists assembled a 1,600-tonne tunnel boring machine (TBM)[1] set to begin excavating the second bore of the Bromford Tunnel into central Birmingham next spring.
The behemoth machine joins ‘Mary Ann’, the first TBM already 0.6 of a mile into digging the tunnel’s first bore since its launch in August 2023[2][3]. Once the newly assembled TBM receives a name and initiates drilling operations, HS2 will have two giants burrowing on a 24/7 basis to complete the project’s 3.5-mile route under North Warwickshire and into Birmingham’s Washwood Heath[3].

While future legs of High Speed 2 have faced recent uncertainty and proposed cutbacks to their scope, construction on the project’s initial core links continues advancing at high speed.
This milestone underscores recent construction momentum for HS2, with over 9,750 people working on HS2 in the West Midlands. “We’re now at peak construction, with over 9,750 people working on HS2 in the West Midlands and around 450 people working on this site, including many from the local area,” said HS2’s Senior Project Manager Catherine Loveridge[4].
Most of the new machine has been reused from the TBM ‘Dorothy’ that completed the Long Itchington Wood Tunnel excavation in Warwickshire earlier this year[5]. BBV’s Tunnelling Director Jules Arlaud said, “Getting to this stage has required a huge amount of planning and preparation, including the disassembly and transportation of 'Dorothy' parts from Warwickshire, which forms the majority of the second TBM”[6].
The machine was assembled by a team of 90 specialist engineers[1] and will be operated around the clock by a specialist tunnelling team, including apprentices working for Tunnelcraft, a sub-contractor to HS2’s principal contractor Balfour Beatty VINCI (BBV)[7]. Arlaud added, “Over the next few months, the team will be busy testing, checking and carrying out the final preparations, to make sure the machine is ready to start digging in spring next year”[6].
The mammoth undertaking will see both TBMs remove 1.87 million tonnes of excavated material as they drive their respective bores, with each bore taking around 16 months[8]. The material will be transported back for sifting and reuse at nearby HS2 construction sites.
Producing the tunnel will require 41,594 concrete segments, forming 5,942 rings, to line its walls as the TBMs move forward[8]. The segments are produced at BBV’s pre-cast factory at Avonmouth near Bristol[8] using high-strength concrete with reduced cement content and emissions. 3D scanning is used in the production process of the segments to guarantee accuracy[8].
Rosa Diez, Tunnels Discipline Lead for MMSDJV, said of the tunnelling already done: “We have learnt so much from the excavation of the Long Itchington Tunnel by our 'Dorothy' TBM, which has helped get 'Mary Ann' well on her way through the Mercia Mudstone in the Bromford Tunnel. The learning will continue for this second TBM, which once named and launched next year, will also become part of our family”[9].
With peak construction now underway across the route, HS2 continues working toward its forecast range of 2029 to 2033 for initial services[10]. The new infrastructure significantly increases rail capacity in the UK, promotes redevelopment of areas around stations, and meets sustainability goals through zero direct emissions trains and expansive tree planting programs.
Loveridge summed up the milestone of the second Bromford Tunnel boring machine coming online: “With the first TBM 'Mary Ann' well on her way building the tunnel to take high speed trains into central Birmingham's Curzon Street Station, it's fantastic to see the second TBM assembled and being prepared to start digging”[4].
Credit via hs2.org.uk
Sources
10 sources
Second giant HS2 tunnel boring machine gets ready to start digging under Birmingham
A 90-strong specialist team has assembled the 1,600 tonne machine set to build the second bore of Bromford Tunnel
Checked 25 October 2026
Second giant HS2 tunnel boring machine gets ready to start digging under Birmingham
It has already built more than 500 tunnel rings, which is 0.6 miles of the 3.5 mile long tunnel
Checked 25 October 2026
Second giant HS2 tunnel boring machine gets ready to start digging under Birmingham
started digging the first bore from the east portal site near Water Orton in August this year.
Checked 25 October 2026
Second giant HS2 tunnel boring machine gets ready to start digging under Birmingham
We’re now at peak construction, with over 9,750 people working on HS2 in the West Midlands and around 450 people working on this site, including many from the local area.
Checked 25 October 2026
Second giant HS2 tunnel boring machine gets ready to start digging under Birmingham
from TBM ‘Dorothy’ after completing the one-mile twin bore Long Itchington Wood Tunnel in Warwickshire earlier this year.
Checked 25 October 2026
Second giant HS2 tunnel boring machine gets ready to start digging under Birmingham
Over the next few months, the team will be busy testing, checking and carrying out the final preparations,
Checked 25 October 2026
Second giant HS2 tunnel boring machine gets ready to start digging under Birmingham
A specialist tunnelling team, including apprentices working for BBV’s sub-contractor Tunnelcraft will operate the TBM 24/7
Checked 25 October 2026
Second giant HS2 tunnel boring machine gets ready to start digging under Birmingham
A total of 41,594 concrete segments will create 5,942 rings to make the twin bore tunnel
Checked 25 October 2026
Second giant HS2 tunnel boring machine gets ready to start digging under Birmingham
We have learnt so much from the excavation of the Long Itchington Tunnel by our ‘Dorothy’ TBM, which has helped get
Checked 25 October 2026
Rail Update (written statement, HS2 Six-Monthly Report to Parliament: November 2023)
remains within the range of 2029 to 2033
Checked 25 October 2026